Budget
Example
While the estimate sets the scope of your project, the budget outlines the final cost using the actual material and labor costs of your product selection.
|
NO. |
Kitchen Remodel |
BUDGET |
change order |
TOTAL |
|
|
bonds, business license if required |
|
|
0 |
|
1.600 |
PERMIT by owner |
|
|
0.00 |
|
6.000 |
CARPENTRY |
1200 |
|
1200 |
|
6.400 |
MILLWORK, INTERIOR MOLDINGS allowances |
150.00 |
|
150 |
|
6.650 |
sierra corian counters , lavender |
3,399.48 |
|
3,399.48 |
|
9.250 |
DRYWALL Patch for demo by owner |
|
|
0 |
|
9.300 |
Tile Material by owner |
|
|
0 |
|
9.305 |
Tile Labor allowance (based on layout & size) |
700 |
|
700 |
|
9.640 |
NEW MAPLE WOOD FLOORING( 2 coats poly) satin finish. does not include transitions, thresholds, underlayment or vents |
2000 |
|
2000 |
|
10. 800 |
knobs per list |
316.99 |
|
316.99 |
|
11.452 |
Appliances by owner |
|
|
0 |
|
11.455 |
CABINETS per list |
12,503.66 |
|
12503.66 |
|
15.000 |
PLUMBER |
1,200.00 |
|
1,200.00 |
|
15.410 |
Plumbing fixtures (no disposal) includes 2 strainers |
966.73 |
|
966.73 |
|
15.700 |
HVAC toe kick vent allowance |
170.00 |
|
170.00 |
|
16.000 |
Electrician (no dimmers) based on blueprint |
3,840.00 |
|
3,840.00 |
|
16.500 |
LIGHT FIXTURES under cabinet lighting |
530.99 |
|
530.99 |
|
17.000 |
contingency |
800.00 |
|
800.00 |
|
|
|
|
|
|
|
27777.85 |
TOTAL |
27,777.85 |
0.00 |
27,777.85 |
|
|
|
|
| |
|